Highway work to resume in Bonners Ferry

| March 4, 2023 1:00 AM

The final phase of a two-year project will begin Monday, March 6, to extend the three-lane section of U.S. Highway 95 from Alderson Lane to Labrosse Hill Street in Bonners Ferry.

“This project will add wider shoulders, sidewalks and lighting to the highway to make it safer and more in line with features you’d find in city limits,” said Project Manager Phil Stout.

Drivers can generally expect a lane to be open in each direction until construction ends in October. Most work will take place during the day, with some night work and detours possible as intersections and driveways are improved.

Starting next week the intersection at U.S. 95 and Pine Island will be closed for the entire duration of construction so that it can be realigned to lessen the incline on the side street and make it easier to turn on and off the highway. All traffic will be detoured to Mirror Lake Road and Riverside Street, but there may be periods of time as the work allows when local passenger-vehicle traffic will be allowed use the intersection.

“ITD has spent four summers so far building these improvements from the Kootenai River Bridge to Eisenhower Street,” Stout said. “This is the last stretch of a multi-year project.”

Information: itdprojects.org/us95bonnersferry